Tag: frr
-

Atlantis into pressurization tasks – numerous SSME items discussed at FRR
Engineers are heading into a weekend of critical operations for STS-132, as Atlantis undergoes flight pressurization operations on the systems that will aid her journey to the International Space Station (ISS) in a week’s time. Wednesday’s Agency Flight Readiness Review (FRR) focused on one of those systems – the Space Shuttle Main Engines (SSMEs) –…
-

STS-132 FRR approves May 14 launch date – External Tank boost
Wednesday’s Agency Flight Readiness Review (FRR) has approved a May 14 launch date for STS-132, following a very smooth meeting at the Kennedy Space Center (KSC). Among the topics discussed was the mitigation efforts on the problem of foam liberation from the External Tank (ET) intertank region, which has been classed as a resounding success,…
-

STS-132 heads into Agency FRR – Ku-band root cause found
NASA and contractor managers will set STS-132’s launch date during the Agency level Flight Readiness Review (FRR) on Wednesday. No major issues have been noted, while Atlantis continues to behave on Pad 39A, raising the likelihood May 14 will be set as the launch date. Meanwhile, engineers have pinpointed the cause of Discovery’s Ku-band system…
-

STS-132: Engineers successfully resolve hypergolic loading issues
Pad operations continue to track a tight timeline ahead of the targeted May 14 launch, as engineers successfully worked through a number of Interim Problem Reports (IPRs) associated with the ongoing hypergolic loading operations on Atlantis’ stack. All eyes are now on next week’s Agency-level Flight Readiness Review (FRR), which will set the official launch…
-

Mission Operations Directorate FRR Presents STS-132/ULF-4 Special Topics
With less than three weeks to go before the launch of the STS-132 mission, Space Shuttle Program (SSP) managers are gearing up for the second of three Flight Readiness Reviews (FRRs) this week – the SSP FRR. Meanwhile, the MOD has already completed their FRR, presenting special topics for Ascent/Entry and New ISS and Shuttle…
-

NASA Reviews Readiness and Potential Timelines for Atlantis’ Final Mission
Preparations are in full swing for next month’s scheduled launch of Space Shuttle Atlantis on the STS-132/ULF-4 mission to deliver the Russian MRM-1 (Mini-Russian Research Module -1) payload – and six external payloads/batteries via the ICC-VLD (Integrated Cargo Carrier – Vertical Light Deployable) – to the International Space Station (ISS), as the mission heads into…
-

NASA Reviews Readiness and Potential Timelines for Atlantis’ Final Mission
Preparations are in full swing for next month’s scheduled launch of Space Shuttle Atlantis on the STS-132/ULF-4 mission to deliver the Russian MRM-1 (Mini-Russian Research Module -1) payload – and six external payloads/batteries via the ICC-VLD (Integrated Cargo Carrier – Vertical Light Deployable) – to the International Space Station (ISS), as the mission heads into…
-

STS-131 enjoys smooth SSP FRR – Discovery into hypergolic loading
As expected, STS-131 has passed its latest milestone, with the approval to push forward to the Agency level Flight Readiness Review on March 26 – following the conclusion of the SSP (Space Shuttle Program) FRR this week. No issues of note are being worked on Discovery out at Pad 39A, as engineers work through hypergolic…
-

STS-130: Endeavour tracking no major FRR topics as launch pace heats up
With less than two weeks until STS-130’s launch with Endeavour, managers are already setting up the readiness meetings for STS-131 – which is scheduled to launch the following month with Discovery. With Flight Readiness Reviews (FRRs) overlapping the missions, engineers and managers will be working at full pace for several weeks. STS-130: Managers are over…
-

STS-129: Main Engine Ignition Acoustic debate leads FRR
Managers at the STS-129 Agency Flight Readiness Review (FRR) have been discussing an issue relating to an attach point between the aft Reaction Control System and OMS Pod, which may be around 20 flights beyond their predicted fatigue lifespan. Due to potential structural integrity problems via localized acoustics during Main Engine Ignition a forward plan…