Tag: STS-127
-

STS-127: NASA managers recommend mission length increase to 16 days
Due to a conflict with Shuttle Crew Scheduling Constraints (SCSC) rules relating to off duty time during flight, NASA managers have recommended an increase of STS-127 to a 16 day mission (16+0+2). The confirmation came via a PRCB (Program Requirements Control Board) meeting presentation, which also outlined alternative options. The mission length will be under review…
-

Atlantis rollout to Pad 39A – FCV plan set up for STS-125/400
Atlantis has rolled back out to Pad 39A for her re-aligned STS-125 mission to the Hubble Space Telescope. First motion for the stack was registered at 3:54am local time, for a 11am arrival at the pad, after which the vehicle will undergo a hotfire of all three of her Auxiliary Power Units (APUs) tonight. Meanwhile…
-

STS-127: MAF praise as Endeavour’s ET-131 arrives at KSC
External Tank (ET-131) is being safely housed in the Vehicle Assembly Building (High Bay 2E), following its arrival from New Orleans this weekend. Manufactured by the Michoud Assembly Facility (MAF), the team earned praise from managers and astronauts alike, following their successful fight back from schedule issues, and the phenomenal performance of ET-129. ET-131…
-

Atlantis and Endeavour deep in processing for their May get-together
While the majority of engineering concentration on the Flow Control Valve (FCV) flight rationale for Discovery and her STS-119 flight, Atlantis – and Endeavour as her rescue support – currently remain on track for their May date surrounding STS-125. Atlantis STS-125 Latest: With STS-119’s NET (No Earlier Than) only slipping my a matter of a…
-

PRCB Outlines Delta Review for STS-127 – includes SpaceX DTO
With Space Shuttle Endeavour now well into her OPF (Orbiter Processing Facility) flow for her triple duty requirements as LON (Launch On Need) vehicle for STS-119 and STS-125 and her primary mission on STS-127, the Program Requirements Control Board (PRCB) has completed the Delta Launch Site Requirements Review (DLSRR) for STS-127, a critical step toward…
-

Fleet processing involves holiday work – Giant crane dominates KSC skyline
Processing will continue on two orbiters through the Christmas holidays, with work required on both Discovery and Endeavour. Meanwhile, a huge crane has been built up to support the final construction of the 600ft Ares I lightning protection towers at Pad 39B. The bulk of the workforce at the Kennedy Space Center (KSC) belong to…
-

Milestone meeting in January to discuss STS-125’s Hubble launch date
Atlantis’ trip to service the Hubble Space Telescope remains on track for May, although another key milestone meeting is due in early January to discuss the status of the replacement Hubble hardware – which is still undergoing testing. An alternative launch date in November remains an option. STS-125 has been delayed several times from its…
-

Endeavour into STS-127 processing – Discovery ready for STS-119 rollover
Endeavour has finally arrived back to the home comforts of her Orbiter Processing Facility (OPF-2), following her highly successful STS-126 mission. Meanwhile, the pace shows no sign in letting up, with Discovery now powered down for the final time, as she prepares to rollover to the Vehicle Assembly Building (VAB) early in January, ahead of…
-

STS-125’s tank arrives – manifest meeting evaluates Ares I-X and ISS supplies
The replacement tank for Atlantis’ mission to service the Hubble Space Telescope has arrived at the Kennedy Space Center (KSC). ET-130 replaces ET-127 – now flying with Discovery in February – following the delay to STS-125. A manifest meeting has already taken place, which has been tasked with finding solutions to Ares I-X’s place in…
-

STS-119/Discovery rollover date changed as 2009 shuttle schedule realigns
Only around five weeks will separate Endeavour’s return home from her STS-126 mission, and when Discovery is due to rollover to the Vehicle Assembly Building (VAB) ahead of STS-119. Discovery’s upcoming milestones are part of a realigned plan for the 2009 missions. However, STS-119’s launch date advancement has been disapproved by shuttle managers. The S6…