STS-128: SSP FRR creates opening rationale for IFR acceptance
The LO2 Ice Frost Ramps (IFRs) will be modified to mitigate against foam liberation – pending design verification – from ET-133 onwards. However, ET-132 has gained the opening round of “rationale for acceptance” via the Space Shuttle Program (SSP) Flight Readiness Review (FRR), which will be verified by a Safety Panel and up for approval…
-

STS-128: Managers head into FRR debate – Void in suspect IFR highlighted
The Space Shuttle Program (SSP) Flight Readiness Review (FRR) heads into a two day meeting on Tuesday, with the focus on the status of ET-132’s Ice Frost Ramps (IFRs). STS-128 may have to rollback for modifications to the ramps – if managers fail to agree on risk acceptance. Interestingly, documentation on the ramp that has…
-

Risk assessment debate for STS-128 tank – Rollback is a potential option
Meetings are taking place through Friday to work on risk acceptance for two LO2 Ice Frost Ramps (IFRs) on Discovery’s External Tank (ET-132), following a full review of STS-127’s LO2 IFR liberation event during launch. If managers call for foam loss mitigation on the ramps, the STS-128 stack will rollback to the Vehicle Assembly Building…
-

STS-131: Discovery’s processing flow mapped out for STS-128 return
With Discovery deep in preparations for her STS-128 mission, shuttle managers are already mapping out the processing flow for her STS-131 flight – allowing for a smooth transition between the conclusion of STS-128 and her flow towards the 2010 mission. As with all flows, numerous modifications will be carried out on the veteran orbiter, as…
-

CVFA work begins on Discovery – SSP told to focus amid Augustine Review
Work has started on replacing the Check Valve Filter Assembly (CVFA) and associated hardware on Discovery’s left hand Solid Rocket Booster (SRB), as engineers continue to evaluation potential schedule impacts to STS-128’s pad flow. Meanwhile, shuttle manager John Shannon has told the workforce to keep their focus on the missions, pre-empting a forward plan for…
-

Discovery completes dramatic rollout – Unique SRB repairs to take place at Pad
With around three weeks until the launch of STS-128, Discovery has finally arrived at Pad 39A, following a dramatic 10 hour-plus rollout on Tuesday. Once at the pad, engineers will incorporate around a week’s worth of changeouts associated with the left Solid Rocket Booster (SRB), following issues with a Check Valve Filter Assembly (CVFA) –…
-

Understanding ET-131’s rogue foam liberations leads to ET-132 confidence
Although no ill effects were suffered by Endeavour, the problems with her External Tank (ET-131) – both prior and during last month’s launch – called for investigations into the downstream tanks, the latest of which is due to fly with Discovery later this month. Thanks to those evaluations, additional confidence has been gained ahead of…
-

STS-128: Discovery rolls to VAB on Sunday following ET-132 clearance
Shuttle engineers like to check, double check, and check again, whenever there’s a flight safety concern – and that was more than the case with the pull tests that have been conducted on External Tank ET-132, following an increased number of foam liberation events during ET-131’s ride to orbit with Endeavour. The test results show…
-

STS-128: Completed ET-132 intertank pull tests show positive results
The foam liberation from Endeavour’s External Tank (ET-131) intertank may have been a one-off event, as all 26 pull tests on ET-132’s intertank show no signs of weakness in the tank set to fly with Discovery next month. However, minor damage was sustained on the tank after a tube-lock broke loose and fell from scaffolding…
-

Endeavour heads into countdown – Atlantis window damage cleared
Endeavour is now proceeding through the complex ballet of S0007 Launch Countdown operations for Saturday’s launch attempt of STS-127 to the International Space Station (ISS). Meanwhile good news has been reported on the damage sustained by Atlantis’ Window 5 (Pilot window), with mold impression results revealing the defects do not breach the unacceptable depth threshold,…